h0 soil thickness is 10 m and final settlement is
Question:
H
0
soil thickness is 10 m and final settlement is 50 mm = total primary consolidation settlement. After 300 days settlement is 10 mm. Additional time for 50% primary consolidation settlement?
GATE CE
Updated On:
Jul 17, 2024
Show Solution
Verified By Collegedunia
Correct Answer:
1875
Solution and Explanation
The correct answer is : 1875 Days
Download Solution in PDF
Was this answer helpful?
0
2
Top GATE CE Questions
If
\(1+\frac{1}{2}+\frac{1}{3}+\frac{1}{4}+\frac{1}{5}+\frac{1}{6}+\frac{1}{7}+\frac{1}{8}+\frac{1}{9}....\frac{1}{29} =\frac{N}{29!}\)
Find the remainder when N is divided by 19.
GATE CE
Divisibility and Remainder
View Solution
What will be the relative density?
M = 0.5 percentage of air voids
γ
min
= 1.3 gm/cc
γ
max
= 1.8 gm/cc
GATE CE
Uplift pressure
View Solution
Find RL of R?
RL of P [BM = 200.000
Point
Staff Readings
Back side
Staff Readings
Fore side
Remarks
P
-2.050
-
200.000
Q
1.050
0.95
Change Point
R
-
-1.655
-
GATE CE
Construction Management
View Solution
What will the angle of the failure plane from horizontal for sand be?
σ
3
=300
σ
1
=300+100=400
GATE CE
Seepage through soils
View Solution
Which of the following having negative skamptam Pore water coefficient?
GATE CE
Channel Hydraulics
View Solution
View More Questions