Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which Contractor X has competed against Contractor Y is given in the Table.\[\begin{array}{|c|c|} \hline \textbf{Ratio of Y's bid price to X's cost} & \textbf{Number of bids} \\ \hline \text{1.02} & \text{6} \\ \hline \text{1.04} & \text{12} \\ \hline \text{1.06} & \text{3} \\ \hline \text{1.10} & \text{6} \\ \hline \text{1.12} & \text{3} \\ \hline \end{array}\]Based on the bidding behaviour of Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is