A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the table.

The total float of the activity “V” (in weeks, in integer) is _______________
| Activity | Duration (Days) | Depends on |
| A | 8 | - |
| B | 4 | A |
| C | 4 | B |
| D | 4 | C, L |
| F | 4 | A |
| G | 4 | F |
| H | 6 | G, L |
| K | 10 | A |
| L | 6 | F, K |