A project consists of eight activities. The time required for each activity and its immediate predecessor(s) are given in the table below. 
If the project completion time using critical path method (CPM) is 15 days, then the value of X (in days) is _________.
The hole and the shaft dimensions (in mm) are given as
Hole dimension = \(30 \pm 0.04\) and Shaft dimension = \(30 \pm 0.06\).
The maximum possible clearance (in mm) is .......... (Rounded off to two decimal places)
A through hole of 10 mm diameter is to be drilled in a mild steel plate of 30 mm thickness. The selected spindle speed and feed for drilling hole are 600 revolutions per minute (RPM) and 0.3 mm/rev, respectively. Take initial approach and breakthrough distances as 3 mm each. The total time (in minute) for drilling one hole is ______. (Rounded off to two decimal places)
In a cold rolling process without front and back tensions, the required minimum coefficient of friction is 0.04. Assume large rolls. If the draft is doubled and roll diameters are halved, then the required minimum coefficient of friction is ___________. (Rounded off to two decimal places)