Step 1: One-day work of each. A does \(\dfrac{1}{12}\), B does \(\dfrac{1}{15}\). Step 2: Combined one-day work. \(\dfrac{1}{12}+\dfrac{1}{15}=\dfrac{5+4}{60}=\dfrac{9}{60}=\dfrac{3}{20}\). Step 3: Total time. Time \(=\dfrac{20}{3}=6\tfrac{2}{3}\) days. \[\boxed{6\tfrac{2}{3}\ \textrm{days}}\]