Question:

Explain the following limitation of planning :
(i) Planning leads to rigidity

Show Hint

A plan fixes goals, time frame and course of action in advance. Managers may not be able to change it when circumstances change. Following a pre-decided plan in changed conditions may harm the organisation.
Updated On: Oct 26, 2026
Show Solution
collegedunia
Verified By Collegedunia

Solution and Explanation

Concept:

• Rigidity of plans: A plan is a pre-decided course of action to be followed within a fixed time frame.

• Planning vs. flexibility: The more detailed and binding a plan is, the less room managers have to adapt it.
Step 1: Explain how plans are drawn up
In an organisation a well-defined plan is drawn up with specific goals to be achieved within a specific time frame. These plans then decide the future course of action, and managers may not be in a position to change them.

Step 2: Explain why this is a limitation
This kind of rigidity in plans may create difficulty. Following a pre-decided plan when circumstances have changed may not turn out to be in the interest of the organisation.